Ecoterraces Project Timeline
Project Duration: May 2007 - 2011 Phase
1: 63 Booth Street, 91 London Road (2007-2008) Phase
2: 4 & 6 Victoria Street, 107-109 London Road (2009)
Phase 3: Woodlands House, 46 London Road (2010)
Timeline Summary
| Feasibility |
May-Sep 2007 |
EcoHomes documents prepared |
| Planning |
Oct-Dec 2007 |
All Phase 1 approvals received |
| Pre-Construction |
Jan 2008 |
Contract start 22 Jan |
| Construction Phase 1 |
Jan-May 2008 |
Main build phase |
| Completion Phase 1 |
May 2008 |
Official opening 12 May |
| Handover |
Jun 2008 |
Tenant occupancy begins |
| Monitoring |
Nov 2008-2011 |
Performance data collection (3 years) |
| Year 1 Report |
Apr 2010 |
Performance gap identified |
| Phase 3 Start |
Jun 2010 |
Woodlands House construction begins |
| Phase 3 Complete |
Late 2010 |
Woodlands House completed |
Detailed Chronology
2007: Feasibility & Planning
May 2007
- 21 May: EcoHomes initial documents prepared
- *Source: Eco-Terraces(attached to Project)
September 2007
- 20 Sep: Design/Scheme discussion - Letter of Intent
meeting
- Source: Messagesof Intent_Build Costs
October 2007
- 15 Oct: 63 Booth Street planning decision
expected
- 18 Oct: EcoHomes Project Group meeting
- Source: Messagesapplication\63 Booth Street Planning
acknowledgement
December 2007
- 11-12 Dec: Planning permissions approved
- 63 Booth Street - Approved
- 91 London Road - Approved
- 4 & 6 Victoria Street - Approved (no conditions)
- 14 Dec: Party Wall Act notice issued (93 London
Road)
- 20 Dec: EcoHomes Project Group meeting
(Newcastle)
- Source: MessagesapplicationCondition Documents
2008: Construction &
Completion
January 2008
- 10 Jan: EcoHomes Assessment specification meeting
(SHA offices)
- 14 Jan: Progress meeting
- 17 Jan: Specification clarification (63 Booth St
& 91 London Rd)
- 22 Jan: CONTRACT START / START ON
SITE
- 24 Jan: EcoHomes Project Group meeting
- Source: MessagesDocuments
February 2008
- 11 Feb: First Progress meeting on site
- 25 Feb: Design revisions - 63 Booth St Rev E
- Source: Messagesmeeting dates
March 2008
- 5 Mar: Site meeting - practical completion
review
- 10 Mar: Progress meeting
- 11-18 Mar: Window installations (rear windows,
external doors)
- 20 Mar: EcoHomes meeting - assessment report
due
- 26 Mar: Target practical completion date
- Source: MessagesMeeting - Phs 1
April 2008
- 7 Apr: Progress meeting
- 10 Apr: Electrical installations target
completion
- 17 Apr: EcoHomes Project Group meeting
- Source: Messagesof EcoHomes Project Group 17 April 08
May 2008
- 1 May: Staffordshire Housing EcoHomes tender
interview
- 2 May: Front windows production complete
- 5 May: Front windows delivery (Bank Holiday
week)
- 7 May: Sound testing - 63 Booth St (10:00-11:00)
& 91 London Rd (11:30-12:30)
- 9 May: Cladding fixings scheduled
- 12 May: ECO-TERRACES OFFICIAL OPENING &
LAUNCH EVENT
- Time: 12:00pm (arrivals 11:30am)
- Location: 91 London Road
- Lunch: 1:00pm
- Source: Messagesto eco terrace opening
June 2008
- 12 Jun: Target handover date - 91 London Road
- 16 Jun: Tenant occupancy commencement (91 London
Road)
- 30 Jun week: Remaining window delivery (91 London
Road)
- Source: Messages\91 London Road Urgent
July 2008
- 10 Jul: EcoHomes Project Group meeting
- Source: Messagesof Ecohomes meeting
November 2008
- 13 Nov: EcoHomes Project Group meeting
- 20 Nov: 2008 Building Awards recognition
- 21 Nov: First formal meter reading
visit (Hockerton Housing monitoring begins)
- 26 Nov: Interim payment certificate received
- Source: Messages\1st stage meter reading
2009: Phase 2 & Monitoring
Early 2009
- NSRP Development Group report for £100k monitoring budget
approval
- Monitoring program continuation
February 2009
- 10 Feb: 46 London Road (Woodlands House) planning
decision
- Application No: 09/0073/FUL
- Source: EcoterracesApplication\46, London Road
2009
- 107/109 London Road: Planning approval
confirmed
- Officer processing and recommendation for approval
- Source: Ecoterraces Phase 2Applicationapproval
2010: Phase 3 (Woodlands
House) & Monitoring
March 2010
- 15 Mar: Woodlands House specification document
issued
- Landscape drawings prepared (RL161 series)
- *Source: Woodlands House
April 2010
- 22 Apr: Year 1 Interim Monitoring
Report delivered by Hockerton Housing Project
- Performance gap identified: space heating 107-130% higher than SAP
predictions
May 2010
- 20 May: Woodlands House Pre-start meeting held
- Source: Woodlands Housestart meeting minutes
June 2010
- 3 Jun: Collaborative Programming Workshop
preparation
- 8 Jun: Collaborative Programming
Workshop at Thomas Vale Construction, Stoke-on-Trent
- Attendees: Axis Design, Poole Dick Associates, Thomas Vale
Construction, Staffs Housing
- 11 action items generated
- 16 Jun: Construction drawings issued (Rev B)
- 28 Jun: Target commencement date for Woodlands
House
- PV installation planning underway
- *Source: Woodlands House
July 2010
- 14 Jul: Grant confirmation received for Woodlands
House
- Funding secured through emergency budget approval process
- Source: Woodlands Houseconfirmation
July-September 2010
- 26 Jul: Phase 1/2 Air test results scheduling
- 20 Aug: Air test results follow-up
- 7 Sep: Air test results follow-up
- Source: MessagesTest Results
August 2010
- 31 Aug: Woodlands House commencement date
discussions
- Source: Woodlands HouseDate
November 2010
- 4 Nov: Pre-start meeting minutes follow-up
- Construction progressing on Woodlands House
- Source: Woodlands Housestart meeting minutes
Late 2010
- Woodlands House construction completed
- Two units: Plot 1 (2-bed, SAP 85) and Plot 2 (3-bed, SAP 89)
- No monitoring program established for Phase 3
Property-Specific Timelines
63 Booth Street
| Dec 2007 |
Planning approved |
| 22 Jan 2008 |
Contract start |
| 26 Mar 2008 |
Practical completion (target) |
| 7 May 2008 |
Sound testing |
| 12 May 2008 |
Opening event |
| 21 Nov 2008 |
First meter reading |
| 2008 |
EcoHomes Excellent achieved |
91 London Road
| Dec 2007 |
Planning approved |
| 22 Jan 2008 |
Contract start |
| 26 Mar 2008 |
Practical completion (target - delayed) |
| 7 May 2008 |
Sound testing |
| 12 May 2008 |
Opening event |
| 12 Jun 2008 |
Handover |
| 16 Jun 2008 |
Tenant occupancy |
| 21 Nov 2008 |
First meter reading |
| 2010 |
Air tightness: 8.1 m³/(h·m²) |
Phase 2 Properties
| 4 & 6 Victoria Street |
Planning approved Dec 2007 |
| 107/109 London Road |
Planning approved 2009 |
Phase 3: Woodlands House
(46 London Road)
| Feb 2009 |
Planning decision (09/0073/FUL) |
| 15 Mar 2010 |
Specification issued |
| 20 May 2010 |
Pre-start meeting |
| 8 Jun 2010 |
Collaborative Programming Workshop |
| 16 Jun 2010 |
Construction drawings issued |
| 28 Jun 2010 |
Target commencement |
| 14 Jul 2010 |
Grant confirmation received |
| Late 2010 |
Construction completed |
| - |
No monitoring undertaken |
Key Specifications: - Plot 1: 77.94 m², SAP 85, 0.50
kWp PV - Plot 2: 103.14 m², SAP 89, 2.00 kWp PV
Critical Path Summary
Phase 1 (2007-2008)
Planning Approval (Dec 2007)
↓
Contract Start (22 Jan 2008)
↓
Construction Phase (Jan-Apr 2008)
↓
Testing & Certification (May 2008)
↓
Official Opening (12 May 2008)
↓
Tenant Handover (Jun 2008)
↓
Monitoring Program (Nov 2008 onwards)
↓
Year 1 Report (Apr 2010) - Performance gap identified
Phase 3 (2010)
Planning Approval (Feb 2009)
↓
Specification Issue (Mar 2010)
↓
Pre-start Meeting (May 2010)
↓
Collaborative Workshop (Jun 2010)
↓
Grant Confirmation (Jul 2010)
↓
Construction (Jun-Nov 2010)
↓
Completion (Late 2010)
↓
No Monitoring Undertaken
Source Files
Phase 1/2
- Planning:
Messages\Planning application\
- Contracts:
Messages\Contract\
- Progress:
Messages\Contacts\Progress meeting dates
- EcoHomes:
Messages\Ecohomes\
- Monitoring:
Messages\Monitoring\
Phase 3 (Woodlands House)
- Specification:
Woodlands House\Files\Specification\
- Drawings:
Woodlands House\Files\Tender drawings\
- SAP Data:
Woodlands House\Files\Ecohomes info\
- Messages:
Woodlands House\Messages\
Source: Basecamp project archive 2007–2011. 834 MB, 759+ message threads, 2,352+ files. Analysis generated January 2026.