Ecoterraces Project Timeline

Project Duration: May 2007 - 2011 Phase 1: 63 Booth Street, 91 London Road (2007-2008) Phase 2: 4 & 6 Victoria Street, 107-109 London Road (2009) Phase 3: Woodlands House, 46 London Road (2010)


Timeline Summary

Phase Period Key Milestone
Feasibility May-Sep 2007 EcoHomes documents prepared
Planning Oct-Dec 2007 All Phase 1 approvals received
Pre-Construction Jan 2008 Contract start 22 Jan
Construction Phase 1 Jan-May 2008 Main build phase
Completion Phase 1 May 2008 Official opening 12 May
Handover Jun 2008 Tenant occupancy begins
Monitoring Nov 2008-2011 Performance data collection (3 years)
Year 1 Report Apr 2010 Performance gap identified
Phase 3 Start Jun 2010 Woodlands House construction begins
Phase 3 Complete Late 2010 Woodlands House completed

Detailed Chronology

2007: Feasibility & Planning

May 2007

September 2007

October 2007

December 2007


2008: Construction & Completion

January 2008

February 2008

March 2008

April 2008

May 2008

June 2008

July 2008

November 2008


2009: Phase 2 & Monitoring

Early 2009

February 2009

2009


2010: Phase 3 (Woodlands House) & Monitoring

March 2010

April 2010

May 2010

June 2010

July 2010

July-September 2010

August 2010

November 2010

Late 2010


Property-Specific Timelines

63 Booth Street

Date Milestone
Dec 2007 Planning approved
22 Jan 2008 Contract start
26 Mar 2008 Practical completion (target)
7 May 2008 Sound testing
12 May 2008 Opening event
21 Nov 2008 First meter reading
2008 EcoHomes Excellent achieved

91 London Road

Date Milestone
Dec 2007 Planning approved
22 Jan 2008 Contract start
26 Mar 2008 Practical completion (target - delayed)
7 May 2008 Sound testing
12 May 2008 Opening event
12 Jun 2008 Handover
16 Jun 2008 Tenant occupancy
21 Nov 2008 First meter reading
2010 Air tightness: 8.1 m³/(h·m²)

Phase 2 Properties

Property Key Milestone
4 & 6 Victoria Street Planning approved Dec 2007
107/109 London Road Planning approved 2009

Phase 3: Woodlands House (46 London Road)

Date Milestone
Feb 2009 Planning decision (09/0073/FUL)
15 Mar 2010 Specification issued
20 May 2010 Pre-start meeting
8 Jun 2010 Collaborative Programming Workshop
16 Jun 2010 Construction drawings issued
28 Jun 2010 Target commencement
14 Jul 2010 Grant confirmation received
Late 2010 Construction completed
- No monitoring undertaken

Key Specifications: - Plot 1: 77.94 m², SAP 85, 0.50 kWp PV - Plot 2: 103.14 m², SAP 89, 2.00 kWp PV


Critical Path Summary

Phase 1 (2007-2008)

Planning Approval (Dec 2007)
    ↓
Contract Start (22 Jan 2008)
    ↓
Construction Phase (Jan-Apr 2008)
    ↓
Testing & Certification (May 2008)
    ↓
Official Opening (12 May 2008)
    ↓
Tenant Handover (Jun 2008)
    ↓
Monitoring Program (Nov 2008 onwards)
    ↓
Year 1 Report (Apr 2010) - Performance gap identified

Phase 3 (2010)

Planning Approval (Feb 2009)
    ↓
Specification Issue (Mar 2010)
    ↓
Pre-start Meeting (May 2010)
    ↓
Collaborative Workshop (Jun 2010)
    ↓
Grant Confirmation (Jul 2010)
    ↓
Construction (Jun-Nov 2010)
    ↓
Completion (Late 2010)
    ↓
No Monitoring Undertaken

Source Files

Phase 1/2

Phase 3 (Woodlands House)

Source: Basecamp project archive 2007–2011. 834 MB, 759+ message threads, 2,352+ files. Analysis generated January 2026.