Ecoterraces Technical Specifications

Phase 1 Certification: EcoHomes Excellent (63 Booth Street, 91 London Road) Phase 3 Certification: EcoHomes targeted (Woodlands House - SAP 85-89)


Performance Summary

Phase 1 (63 Booth St, 91 London Rd)

Metric Target/Achieved Notes
EcoHomes Rating Excellent 0.18% above threshold
Air Tightness 8.1 m³/(h·m²) @ 50Pa 91 London Road
Roof U-value 0.147 W/m²K 300mm Warmcel
Window U-value 1.5 W/m²K Upgraded from 1.6
Door U-value 1.9 W/m²K 58mm thick
Ventilation Sunwarm passive solar Heat recovery
Code Level 3-4 achievable 44% better than Part L

Phase 3 (Woodlands House)

Metric Plot 1 (2-bed) Plot 2 (3-bed)
SAP Rating 84.99 (Band B) 88.97 (Band B)
DER (kg CO₂/m²/a) 22.08 16.67
Floor Area 77.94 m² 103.14 m²
Wall U-value 0.35 W/m²K 0.35 W/m²K
Roof U-value 0.15 W/m²K 0.15 W/m²K
Floor U-value 0.25 W/m²K 0.25 W/m²K
Window U-value 1.5 W/m²K 1.5 W/m²K
PV System 0.50 kWp 2.00 kWp
Ventilation Individual fans + HR Whole-house MVHR

1. Energy Performance

SAP Ratings & Building Regulations

63 Booth Street - EcoHomes: Excellent (final certificate received) - Exceeded threshold by 0.18% above requirements

91 London Road - EcoHomes score: Calculation in progress at time of archive - Air tightness test: Completed

Code for Sustainable Homes Capability - Level 3: Achievable (Newcastle Borough Council requirement) - Level 4: Potentially achievable (44% better than Part L) - Level 5-6: Not feasible (require 100% better / Zero Carbon)

Air Tightness Testing

Property Result Status
63 Booth Street Certified Complete
91 London Road 8.1 m³/(h·m²) @ 50Pa Test complete, cert pending

Testing conducted May 2008


2. Thermal Envelope

Roof Insulation

Specification Value
Material Warmcel (cellulose-based)
Thickness 300mm
U-value 0.147 W/m²K
Alternative Kingspan products evaluated
Note Based on timber battens (metal would reduce performance)

Windows

Specification Value
U-value 1.5 W/m²K (upgraded from 1.6)
Supplier Howarth Timber
Frame Timber or Composite
Composite option Velfac (market leaders)
Glazing 24mm sealed units

Doors

Specification Value
U-value 1.9 W/m²K
Thickness 58mm
Panels Insulated
Security glazing Laminated (Secured by Design / PAS24)

Thermal Details


3. M&E Specifications

Heating System

Component Specification
Boiler Worcester-Bosch Greenstar Junior 28i
Fuel Gas (primary)
Distribution Standard radiator system

Hot Water

Component Specification
Bath water Gas boiler
Shower Electric (8.5-9.5 kW) - primary source
Immersion None specified
Recovery Via boiler and Nuaire system

Ventilation

System Application
Nuaire Positive pressure ventilation (selected properties)
Sunwarm Heat recovery with unglazed collector
Passive Stack Option for 1 of 4 properties (free Nuaire installation)
Strategy Varying approaches tested across properties

Solar/Renewable

Feature Details
Solar gain spaces Glazed wall/roof rear extensions
Purpose Primary: energy savings; Secondary: floor space
Glazing Single glazed cavities (no double glazing)
Funding LCP Programme eligible (Sunwarm)

4. Electrical Systems

Metering Configuration

Meter Specification
Supplier Universal Meter Services
Model Iskra ME160 & ME161
Type Analogue and electronic
Size 140mm x 100mm
Cost £25-40 per meter

Circuit Metering Strategy

Baseline Meter Readings (Handover)

Meter 63 Booth St 91 London Rd
Gas (units) 659 4492
Electric (units) 21031 2894
Boiler (units) 69 26
Lighting (units) 110 71
Shower (units) 0 1
Heat Exchanger (units) 57 64
Water Heater (units) 0 0
House Ring Main (units) 9 17

Lighting

Specification Value
Initial target 40-75% low voltage
Final approach 100% low energy dedicated fittings
Type Cannot accept standard incandescent
LED Pursued as low energy qualification

5. EcoHomes Requirements

Assessment Credits

Category Requirement
Global Warming Potential Data from insulation manufacturers
Construction Site Impacts Documentation required
Daylight levels Affected by nearby houses
Sound testing AEC Ltd (7 May 2008)
Security glazing Laminated to rear (PAS24)

Responsible Sourcing Evidence Required

White Goods (for Excellent Rating)

Appliance Model Rating Capacity
Washing Machine Matsui MWM145 A 42L drum
Fridge-Freezer Indesit BAAN10 A+ 249L

6. Materials & Finishes

Flooring

Location Material
Main areas Bamboo (15mm thick)
Kitchen Non-slip (level with bamboo)
Ground floor WC Non-slip
Stairs/Landing Carpet
Bedrooms Carpet

Sanitary

Item Specification
WC Ideal Standard Spacesaver
Flush 6/4 litre dual flush
Standard EcoHomes compliant

External

Item Specification
Shed 1.8m x 2.4m minimum (3-bed requirement)
Bike storage Lockable bar fixing
Water connection Severn Trent - Project 15/286336

Cooker Hoods


7. Monitoring Program

Framework

Element Details
First reading 21 November 2008
Coordinator Hockerton Housing Trust (Nick)
Duration 24+ months
Data Energy consumption patterns
Survey Anecdotal resident feedback

Metering Approach


8. Code for Sustainable Homes Reference

Level Requirement Achievability
Level 3 Standard Achievable
Level 4 44% better than Part L Potentially achievable
Level 5 100% better than Part L Not feasible
Level 6 Zero Carbon Not feasible

Note: Code applies to new build; EcoHomes applies to refurbishment


9. Phase 3: Woodlands House (46 London Road)

Woodlands House was a retrofit of an Edwardian semi-detached property at 46 London Road, representing an evolution in the Ecoterraces approach - moving away from passive solar techniques toward improved fabric specifications and photovoltaic systems.

Building Overview

Parameter Plot 1 (Rear 2-Bed) Plot 2 (Front 3-Bed)
Total Floor Area 77.94 m² 103.14 m²
Ground Floor 40.12 m² 54.60 m²
First Floor 37.82 m² 48.54 m²
Dwelling Volume 227.40 m³ 308.81 m³
Storey Height (GF) 2.84 m 2.90 m
Storey Height (FF) 3.00 m 3.10 m

SAP Energy Performance

Parameter Plot 1 Plot 2
TER (Target) 23.61 kg CO₂/m²/a 22.81 kg CO₂/m²/a
DER (Achieved) 22.08 kg CO₂/m²/a 16.67 kg CO₂/m²/a
SAP Rating 84.99 (Band B) 88.97 (Band B)
EI Rating 81 (Band B) 84 (Band B)
Compliance Pass (DER < TER) Pass (DER < TER)

Predicted Annual Energy Consumption

Component Plot 1 Plot 2
Space Heating (Main) 4,184 kWh 5,791 kWh
Space Heating (Secondary 10%) 418 kWh 579 kWh
Water Heating 3,045 kWh 3,465 kWh
Pumps/Fans 130 kWh 130 kWh
Lighting 591 kWh 783 kWh
Total Primary Energy 10,738 kWh 11,375 kWh
Energy Intensity 137.77 kWh/m²/yr 110.29 kWh/m²/yr
CO₂ Emissions 1,721 kg/yr 1,720 kg/yr

Thermal Envelope (Phase 3)

Element U-Value Notes
External Walls 0.35 W/m²K Solid brick insulated
Ground Floor 0.25 W/m²K Solid/suspended insulated
Cold Roof 0.15 W/m²K Cold roof insulation
Windows 1.50 W/m²K Timber mock sash
Doors 2.40 W/m²K Timber
Air Permeability 8.00 m³/(h.m²) @ 50Pa Design target

Heating System (Phase 3)

Specification Details
Boiler Worcester-Bosch 30CDi
Type Sedbuk A-rated condensing combi
Efficiency 90% (minimum 86%)
Hot Water Direct from combi (no cylinder)
Controls Thermostat, 7-day programmer, TRV
Interlock Boiler interlock fitted

Ventilation Systems (Phase 3)

Plot 1 (2-Bed): - Kitchen: Vent Axia HD25 with heat recovery - Bathroom: Vent Axia HD25 with heat recovery - WC: Individual through-wall fans - Air permeability: 8.00 m³/(h.m²) @ 50Pa

Plot 2 (3-Bed): - System: Vent Axia Sentinel Kintec B (whole-house MVHR) - Fans: 3 intermittent fans/passive vents (30 m³/hr) - Air permeability: 8.00 m³/(h.m²) @ 50Pa

Renewable Energy (Phase 3)

Plot PV Capacity Annual Production
Plot 1 0.50 kWp 319 kWh/year
Plot 2 2.00 kWp 1,276 kWh/year

Note: Plot 2’s larger PV system (4x capacity) contributes to better per-m² energy performance despite 33% larger floor area.

Water Efficiency (Phase 3)

Item Specification
WC Twyford Galerie dual flush 6/4 litre
Bath Twyford Signature 140-litre capacity
Taps Lo-flow mixer with Aquation technology
Kitchen Sink 6-litre aerator

Materials (Phase 3)

Material Specification
Structural Timber 100% FSC certified
Finishing Timber 100% FSC certified
Concrete 100% recycled aggregate (RCA)
Flooring Softwood T&G boards (existing retained where possible)
External Roof tiles and bricks reused from existing structure

EcoHomes Credits (Phase 3)

Credit Requirement Solution
Ene3 Drying facilities Rotary drying line in garden
Ene5 Low-energy lighting 100% dedicated Newlec 4-pin fluorescent
Ene6 External lighting Dawn till dusk lights
Tra2 Cycle storage 1.8m x 2.4m shed with locking point
Tra4 Home office 2 x 2-gang sockets + double telephone on 1.8m wall
Mat4 Recycling Howden Triple Waste bin (40 litres)
Wat1 Water efficiency Dual flush 6/4 litre toilets
Wat2 Rainwater 220 litre Polybutt water butt
Man2 Construction Considerate Contractors score 32-40
Man4 Security Secured by Design (ALO: PC David Elkington)

Key Differences: Phase 1 vs Phase 3

Aspect Phase 1 Phase 3
Project Type Refurbishment Retrofit (Edwardian semi-detached)
Passive Solar Sunwarm system Not used
PV System None 0.50-2.00 kWp
Ventilation Sunwarm heat recovery MVHR / Individual fans
Roof U-value 0.147 W/m²K 0.15 W/m²K
Wall U-value Not specified 0.35 W/m²K
SAP Rating 76-77 85-89
Monitoring 3-year program None undertaken

Source Files

Phase 1/2

Phase 3 (Woodlands House)

Source: Basecamp project archive 2007–2011. 834 MB, 759+ message threads, 2,352+ files. Analysis generated January 2026.