Monitoring Period: July 2008 - 2011 (extended to 3 years) Budget: £30,000 (originally 2-year, extended) Coordinator: Hockerton Housing Project (Nick Martin, Rob Cartwright) Year 1 Report: 22 April 2010
📊 Download Year 1 Interim Report (PDF)
The Ecoterraces project established a systematic monitoring program linking design specifications to post-occupancy performance verification. The Year 1 interim report (April 2010) revealed a significant performance gap - while EcoHomes Excellent certification was achieved, actual energy consumption exceeded SAP predictions, particularly for space heating.
Key Finding: Space heating energy was 107-130% higher than SAP predictions, likely due to Sunwarm system underperformance or user error.
Positive Result: Total energy consumption was still 27-30% better than UK averages for equivalent property types.
| Metric | 63 Booth Street | 91 London Road |
|---|---|---|
| Total Annual Energy | 13,516 kWh | 16,137 kWh |
| Annual CO₂ Emissions | 3.02 tCO₂ | 4.18 tCO₂ |
| Annual Running Cost | £757.68 | £1,142.86 |
| Hot Water Consumption | 33.16 m³ | 40.28 m³ |
| Actual Occupancy | 1 adult, 1 child | 2 adults, 2 children |
| SAP Assumed Occupancy | 2.46 | 2.71 |
| Meter | Annualized (kWh) |
|---|---|
| Main Electric | 1,749 |
| Central Heating Pump | 257 |
| Sunwarm Pump | 193 |
| Immersion Heater | 0 |
| Lighting | 215 |
| Electric Shower | 65 |
| General Ring Main | 315 |
| Gas | 11,767 |
| Meter | Annualized (kWh) |
|---|---|
| Main Electric | 4,583 |
| Central Heating Pump | 239 |
| Sunwarm Pump | 191 |
| Immersion Heater | 47 |
| Lighting | 416 |
| Electric Shower | 587 |
| General Ring Main | 1,030 |
| Gas | 11,554 |
| Property | SAP Predicted | Actual | Variance |
|---|---|---|---|
| 63 Booth Street | 4,691 kWh/yr | 10,758 kWh/yr | +130% |
| 91 London Road | 5,414 kWh/yr | 11,179 kWh/yr | +107% |
Space heating per m²: - 63 Booth St: 140.4 kWh/m²/yr (SAP predicted: 61.2) - 91 London Rd: 131.2 kWh/m²/yr (SAP predicted: 63.5)
| Property | SAP Predicted | Actual | Variance |
|---|---|---|---|
| 63 Booth Street | 2,383 kWh/yr | 2,208 kWh/yr | -7% |
| 91 London Road | 2,497 kWh/yr | 2,075 kWh/yr | -17% |
| Property | Type | Actual | EST Average | Reduction |
|---|---|---|---|---|
| 63 Booth Street | 3-bed mid-terrace | 13,516 kWh | 18,572 kWh | 27% |
| 91 London Road | 3-bed end-terrace | 16,137 kWh | 22,902 kWh | 30% |
Conclusion: Properties perform significantly better than UK average stock, but fall short of the 44% reduction target for Code Level 4.
The monitoring report identified the Sunwarm ventilation/heat recovery system as the likely source of the performance gap:
| Issue | Property | Impact |
|---|---|---|
| Shower plumbed incorrectly | 63 Booth St | Connected to hot water cylinder instead of mains - forced baths instead of showers |
| Cylinder thermostat set low | 63 Booth St | Set at 43°C (should be 60°C) - shower unusable at correct temp |
| Heating usage patterns | Both | Lower than SAP standard (4 hrs/day vs 9-16 hrs assumed) yet still higher consumption |
| Parameter | 63 Booth Street | 91 London Road |
|---|---|---|
| Total Floor Area | 76.6 m² | 85.2 m² |
| SAP Rating | 77 | 76 |
| Air Pressure Test | 7.78 m³/hr/m² | 8.1 m³/hr/m² |
| Energy Content Hot Water | 1,801 kWh/yr | 1,915 kWh/yr |
| Space Heating (predicted) | 4,691 kWh/yr | 5,414 kWh/yr |
| Primary Energy (predicted) | 12,370 kWh/yr | 13,772 kWh/yr |
| CO₂ Emissions (predicted) | 2,011 kg/yr | 2,239 kg/yr |
| Metric | 63 Booth St (Actual) | 63 Booth St (SAP) | 91 London Rd (Actual) | 91 London Rd (SAP) |
|---|---|---|---|---|
| Primary Energy | 15,992 kWh/yr | 12,370 kWh/yr | 17,432 kWh/yr | 13,772 kWh/yr |
| Primary Energy/m² | 208.8 kWh/m²/yr | 161.6 kWh/m²/yr | 204.6 kWh/m²/yr | 161.6 kWh/m²/yr |
| CO₂ Emissions | 2,591 kg/yr | 2,011 kg/yr | 2,866 kg/yr | 2,239 kg/yr |
| CO₂/m² | 33.8 kg/m²/yr | 26.3 kg/m²/yr | 33.6 kg/m²/yr | 26.3 kg/m²/yr |
Performance vs SAP: ~29% higher primary energy and CO₂ than predicted
| Component | 63 Booth St | 91 London Rd | Notes |
|---|---|---|---|
| Pumps & Fans | 61% less than SAP | 66% less than SAP | SAP defaults overestimate |
| Lighting | 38% less than SAP | 3% more than SAP | Fixed fittings only |
Due to delays in Phase 2 property completion, the monitoring program was extended:
| Original | Revised |
|---|---|
| 2 years | 3 years |
| 6 properties | 2 properties (initially) |
| Quarterly visits | Reduced frequency |
Problem: Space heating 107-130% higher than SAP predictions Suspected Cause: Sunwarm underperformance or user error Evidence: Nuaire identified reversed operation by occupants Action: Occupant training + recommendation for additional metering
Problem: Electric shower plumbed to hot water cylinder, not mains Impact: Water too hot to use shower; resident forced to take baths Resolution: Plumbing corrected Evidence: Only 1kWh shower consumption Mar-Jul 2009
Design assumed: 5.0 m³/(h·m²) Actual achieved: 7.78-8.1 m³/(h·m²) Impact: Slight SAP adjustment, construction quality validated
SAP assumes: 9 hrs/day weekdays, 16 hrs/day weekends Actual (91 London Rd): 4 hrs/day during winter (Nov-Apr) Implication: Even with less heating time, consumption exceeded predictions
| Specification | Target | Verified | Result |
|---|---|---|---|
| Roof U-value | 0.147 W/m²K | Yes | Met (SAP calculation) |
| Window U-value | 1.5 W/m²K | Yes | Met (supplier data) |
| Door U-value | 1.9 W/m²K | Yes | Met (supplier data) |
| Air tightness | <10 m³/(h·m²) | Yes | 7.78-8.1 achieved |
| System | Specification | Monitoring Result |
|---|---|---|
| Worcester-Bosch Boiler | 90.3% efficiency | Performing as specified |
| Sunwarm System | 2,907-3,314 kWh/yr saving | Underperforming - root cause unclear |
| Electric Shower | 7.9kW @ 230v | Working (after plumbing fix) |
| Lighting (fixed) | 100% low-energy | 38% less consumption than SAP (Booth St) |
Phase 1 Learning: Sunwarm system performance concerns Phase 2 Decision: Test varied ventilation strategies across properties Benefit: Nuaire offered free product/installation for comparison testing
Decision: Apply consistent M&E principles from 63 Booth St to other properties Purpose: Enable direct comparison in monitoring data
Learning: Two properties insufficient for conclusive analysis Decision: Extend to 3 years, await Phase 2 occupancy
| Person | Role | Organization |
|---|---|---|
| Nick Martin | Report Author, Monitoring Lead | Hockerton Housing Project |
| Rob Cartwright | Report Author, Data Analysis | Hockerton Housing Project |
| Rob Annable | Lead Architect | Axis Design |
| Tony Clements | SAP Calculations | Energy Consultant |
| Nuaire | System Manufacturer | Sunwarm Analysis |
The Year 1 report raises a critical question: Is the gap due to: - Thermal insulation underperformance? - Central heating system underperformance? - Sunwarm system underperformance? - Combination of all three?
The report concludes Sunwarm is the most likely cause, but additional monitoring data is required for definitive proof.
Despite the performance gap, Ecoterraces demonstrates: - Value of comprehensive post-occupancy monitoring - Importance of system-level metering for diagnosis - Real-world performance can diverge significantly from theoretical models - Occupant behavior and training are critical factors
Important Note: Phase 3 (Woodlands House, 46 London Road) did not have a post-occupancy monitoring program established.
| Aspect | Impact |
|---|---|
| Predicted Performance | SAP calculations only (SAP 85-89) |
| Actual Performance | Unknown - no data collected |
| Technology Validation | PV systems and MVHR untested in real-world conditions |
| Occupant Feedback | Not captured |
| Metric | Phase 1 (Monitored) | Phase 3 (Not Monitored) |
|---|---|---|
| SAP Rating | 76-77 | 85-89 (higher) |
| Predicted Energy | 12,370-13,772 kWh/yr | 10,738-11,375 kWh/yr (lower) |
| Actual Performance | Known (13,516-16,137 kWh) | Unknown |
| Performance Gap | 107-130% space heating | Cannot be verified |
The lack of monitoring for Phase 3 means:
Year 1 interim report V1-2 FINAL.pdf (22 April 2010)Messages\Monitoring\Messages\Energy performance\Messages\Contacts\Air Test Results\Messages\Production Information\M&E spec\