Monitoring Results & Specification Traceability

Monitoring Period: July 2008 - 2011 (extended to 3 years) Budget: £30,000 (originally 2-year, extended) Coordinator: Hockerton Housing Project (Nick Martin, Rob Cartwright) Year 1 Report: 22 April 2010


📊 Download Year 1 Interim Report (PDF)

Executive Summary

The Ecoterraces project established a systematic monitoring program linking design specifications to post-occupancy performance verification. The Year 1 interim report (April 2010) revealed a significant performance gap - while EcoHomes Excellent certification was achieved, actual energy consumption exceeded SAP predictions, particularly for space heating.

Key Finding: Space heating energy was 107-130% higher than SAP predictions, likely due to Sunwarm system underperformance or user error.

Positive Result: Total energy consumption was still 27-30% better than UK averages for equivalent property types.


1. Year 1 Monitoring Results (July 2008 - July 2009)

Annual Energy Consumption Summary

Metric 63 Booth Street 91 London Road
Total Annual Energy 13,516 kWh 16,137 kWh
Annual CO₂ Emissions 3.02 tCO₂ 4.18 tCO₂
Annual Running Cost £757.68 £1,142.86
Hot Water Consumption 33.16 m³ 40.28 m³
Actual Occupancy 1 adult, 1 child 2 adults, 2 children
SAP Assumed Occupancy 2.46 2.71

Annualized Meter Readings

63 Booth Street

Meter Annualized (kWh)
Main Electric 1,749
Central Heating Pump 257
Sunwarm Pump 193
Immersion Heater 0
Lighting 215
Electric Shower 65
General Ring Main 315
Gas 11,767

91 London Road

Meter Annualized (kWh)
Main Electric 4,583
Central Heating Pump 239
Sunwarm Pump 191
Immersion Heater 47
Lighting 416
Electric Shower 587
General Ring Main 1,030
Gas 11,554

2. Performance Gap Analysis

The Critical Finding: Space Heating

Property SAP Predicted Actual Variance
63 Booth Street 4,691 kWh/yr 10,758 kWh/yr +130%
91 London Road 5,414 kWh/yr 11,179 kWh/yr +107%

Space heating per m²: - 63 Booth St: 140.4 kWh/m²/yr (SAP predicted: 61.2) - 91 London Rd: 131.2 kWh/m²/yr (SAP predicted: 63.5)

Hot Water Performance (Better than Predicted)

Property SAP Predicted Actual Variance
63 Booth Street 2,383 kWh/yr 2,208 kWh/yr -7%
91 London Road 2,497 kWh/yr 2,075 kWh/yr -17%

Comparison to UK Averages

Property Type Actual EST Average Reduction
63 Booth Street 3-bed mid-terrace 13,516 kWh 18,572 kWh 27%
91 London Road 3-bed end-terrace 16,137 kWh 22,902 kWh 30%

Conclusion: Properties perform significantly better than UK average stock, but fall short of the 44% reduction target for Code Level 4.


3. Root Cause Analysis

Suspected Primary Cause: Sunwarm System

The monitoring report identified the Sunwarm ventilation/heat recovery system as the likely source of the performance gap:

  1. User Error Identified by Nuaire:
    • Occupants were setting systems to heat in summer and cool in winter (reversed operation)
    • Occupant training recommended
  2. Lack of System Monitoring:
    • Sunwarm delivered energy not metered
    • Unable to verify actual system performance vs. manufacturer claims
    • Recommended: Install flow rate meters and heat meters
  3. SAP Model Limitations:
    • Sunwarm not available as Appendix Q technology in SAP
    • Standard solar hot water system assumed instead
    • Likely overstated predicted contribution

Secondary Issues Identified

Issue Property Impact
Shower plumbed incorrectly 63 Booth St Connected to hot water cylinder instead of mains - forced baths instead of showers
Cylinder thermostat set low 63 Booth St Set at 43°C (should be 60°C) - shower unusable at correct temp
Heating usage patterns Both Lower than SAP standard (4 hrs/day vs 9-16 hrs assumed) yet still higher consumption

4. SAP Parameters Verified

Parameter 63 Booth Street 91 London Road
Total Floor Area 76.6 m² 85.2 m²
SAP Rating 77 76
Air Pressure Test 7.78 m³/hr/m² 8.1 m³/hr/m²
Energy Content Hot Water 1,801 kWh/yr 1,915 kWh/yr
Space Heating (predicted) 4,691 kWh/yr 5,414 kWh/yr
Primary Energy (predicted) 12,370 kWh/yr 13,772 kWh/yr
CO₂ Emissions (predicted) 2,011 kg/yr 2,239 kg/yr

5. Primary Energy & CO₂ Analysis

Actual vs SAP Predicted

Metric 63 Booth St (Actual) 63 Booth St (SAP) 91 London Rd (Actual) 91 London Rd (SAP)
Primary Energy 15,992 kWh/yr 12,370 kWh/yr 17,432 kWh/yr 13,772 kWh/yr
Primary Energy/m² 208.8 kWh/m²/yr 161.6 kWh/m²/yr 204.6 kWh/m²/yr 161.6 kWh/m²/yr
CO₂ Emissions 2,591 kg/yr 2,011 kg/yr 2,866 kg/yr 2,239 kg/yr
CO₂/m² 33.8 kg/m²/yr 26.3 kg/m²/yr 33.6 kg/m²/yr 26.3 kg/m²/yr

Performance vs SAP: ~29% higher primary energy and CO₂ than predicted

Component Breakdown

Component 63 Booth St 91 London Rd Notes
Pumps & Fans 61% less than SAP 66% less than SAP SAP defaults overestimate
Lighting 38% less than SAP 3% more than SAP Fixed fittings only

6. Monitoring Program Updates

Program Extension

Due to delays in Phase 2 property completion, the monitoring program was extended:

Original Revised
2 years 3 years
6 properties 2 properties (initially)
Quarterly visits Reduced frequency

Recommendations from Year 1 Report

  1. Install Sunwarm monitoring equipment:
    • Flow rate meters
    • Heat meters
    • Essential to isolate system performance
  2. Occupant training:
    • Address reversed Sunwarm operation
    • Correct understanding of controls
  3. Fix installation issues:
    • Shower plumbing (completed)
    • Cylinder thermostat settings
  4. Continue temperature logging:
    • Data being collected but not yet analyzed
    • Will be included in final report

7. Issues & Discoveries

7.1 Sunwarm System Performance Gap

Problem: Space heating 107-130% higher than SAP predictions Suspected Cause: Sunwarm underperformance or user error Evidence: Nuaire identified reversed operation by occupants Action: Occupant training + recommendation for additional metering

7.2 Shower Installation Error (63 Booth St)

Problem: Electric shower plumbed to hot water cylinder, not mains Impact: Water too hot to use shower; resident forced to take baths Resolution: Plumbing corrected Evidence: Only 1kWh shower consumption Mar-Jul 2009

7.3 Air Tightness Better Than Design Assumption

Design assumed: 5.0 m³/(h·m²) Actual achieved: 7.78-8.1 m³/(h·m²) Impact: Slight SAP adjustment, construction quality validated

7.4 Heating Usage Lower Than SAP Assumes

SAP assumes: 9 hrs/day weekdays, 16 hrs/day weekends Actual (91 London Rd): 4 hrs/day during winter (Nov-Apr) Implication: Even with less heating time, consumption exceeded predictions


8. Specification-to-Monitoring Traceability

Thermal Envelope

Specification Target Verified Result
Roof U-value 0.147 W/m²K Yes Met (SAP calculation)
Window U-value 1.5 W/m²K Yes Met (supplier data)
Door U-value 1.9 W/m²K Yes Met (supplier data)
Air tightness <10 m³/(h·m²) Yes 7.78-8.1 achieved

Energy Systems - Performance vs Specification

System Specification Monitoring Result
Worcester-Bosch Boiler 90.3% efficiency Performing as specified
Sunwarm System 2,907-3,314 kWh/yr saving Underperforming - root cause unclear
Electric Shower 7.9kW @ 230v Working (after plumbing fix)
Lighting (fixed) 100% low-energy 38% less consumption than SAP (Booth St)

9. Feedback Loops: Phase 1 → Phase 2

Ventilation Strategy Variation

Phase 1 Learning: Sunwarm system performance concerns Phase 2 Decision: Test varied ventilation strategies across properties Benefit: Nuaire offered free product/installation for comparison testing

M&E Standardization

Decision: Apply consistent M&E principles from 63 Booth St to other properties Purpose: Enable direct comparison in monitoring data

Program Extension

Learning: Two properties insufficient for conclusive analysis Decision: Extend to 3 years, await Phase 2 occupancy


10. Key Actors in Monitoring

Person Role Organization
Nick Martin Report Author, Monitoring Lead Hockerton Housing Project
Rob Cartwright Report Author, Data Analysis Hockerton Housing Project
Rob Annable Lead Architect Axis Design
Tony Clements SAP Calculations Energy Consultant
Nuaire System Manufacturer Sunwarm Analysis

11. Conclusions

Year 1 Key Findings

  1. Performance Gap Identified:
    • Space heating 107-130% higher than SAP predictions
    • Hot water 7-17% better than predictions
    • Overall ~29% worse than SAP for primary energy
  2. Root Cause Suspected:
    • Sunwarm system underperformance or user error
    • Lack of system-level metering prevents definitive diagnosis
    • Installation issues (shower plumbing) contributed
  3. Positive Outcomes:
    • 27-30% better than UK average housing stock
    • Air tightness exceeded design assumptions
    • EcoHomes Excellent certification achieved
    • Comprehensive metering infrastructure working
  4. Recommendations:
    • Install Sunwarm flow rate and heat meters
    • Provide occupant training on system operation
    • Continue monitoring with extended program

The Performance Gap Question

The Year 1 report raises a critical question: Is the gap due to: - Thermal insulation underperformance? - Central heating system underperformance? - Sunwarm system underperformance? - Combination of all three?

The report concludes Sunwarm is the most likely cause, but additional monitoring data is required for definitive proof.

Project Legacy

Despite the performance gap, Ecoterraces demonstrates: - Value of comprehensive post-occupancy monitoring - Importance of system-level metering for diagnosis - Real-world performance can diverge significantly from theoretical models - Occupant behavior and training are critical factors


12. Phase 3: Woodlands House - No Monitoring

Important Note: Phase 3 (Woodlands House, 46 London Road) did not have a post-occupancy monitoring program established.

Implications

Aspect Impact
Predicted Performance SAP calculations only (SAP 85-89)
Actual Performance Unknown - no data collected
Technology Validation PV systems and MVHR untested in real-world conditions
Occupant Feedback Not captured

Comparison with Phase 1

Metric Phase 1 (Monitored) Phase 3 (Not Monitored)
SAP Rating 76-77 85-89 (higher)
Predicted Energy 12,370-13,772 kWh/yr 10,738-11,375 kWh/yr (lower)
Actual Performance Known (13,516-16,137 kWh) Unknown
Performance Gap 107-130% space heating Cannot be verified

Lessons

The lack of monitoring for Phase 3 means:

  1. No verification of whether improved specifications (higher SAP ratings, PV systems) delivered predicted performance
  2. No comparison possible between passive solar (Phase 1 Sunwarm) vs. PV/MVHR (Phase 3) approaches
  3. No data to inform future refurbishment projects
  4. The Phase 1 monitoring investment becomes even more valuable as the only source of real-world data

Source Documents

Source: Basecamp project archive 2007–2011. 834 MB, 759+ message threads, 2,352+ files. Analysis generated January 2026.