Site Information Requirements

Podular Planning Guidance

What to request from the client and what to procure through surveys.


From Client

Ownership & Legal

Note: OS plan-based legal documents are often inaccurate vs actual site conditions. Always verify with topographical survey.

Housing Requirements


Utilities Searches

Recommended Approach

Required Utilities

See Appendix A Suppliers for provider details.


Site Investigations

Always Required

Context-Dependent


Environmental Assessments

Mandatory for All Developments

- Small Sites Metric (SSM) for <10 units

- Can be completed by developer (no ecologist required for SSM)

- 30-year habitat management plan required (confirm LPA position)

Context-Dependent

AssessmentTrigger
Tree Survey (BS 5837)Trees present/affected
Preliminary Ecological AppraisalEcological interest beyond BNG
Flood Risk AssessmentFlood zones 2 or 3
Air Quality AssessmentNear Clean Air Zone (check LPA buffer)
Heritage Impact AssessmentAffecting heritage assets
Ground ContaminationBrownfield site

Not Required for Minor Development

Note: "Not required" means not automatically required — LPA may still request. Check Appendix B Lpa Variations.

Planning Context Checks

Before progressing, confirm:


Cross-References